﻿## Define manually
If required, prioritise one or several charging points to which the load management should provide the highest possible charging current as a preference. If the minimum charging current per charging point is guaranteed and current is still available, the prioritised charging points receive it first. The upper limit is the maximum charging current defined for the charging point. If there is still electricity available, it is distributed evenly amongst the other charging points. If an even distribution is impossible (e.g. uneven number of amperes), the order is decisive (1 first, 0 last).